NANCY MADSEN / STAFF WRITER
WEDNESDAY, MARCH 3, 2010
Link to the Watertown Times article -->here<--
CAPE VINCENT - The developer of St. Lawrence Wind Farm will wait to proceed with the next step on the project until the town has passed a zoning law.
Peter E. Zedick, project developer for Acciona Wind Energy USA, told the Times earlier this week, “We’re waiting to see what happens with the town and their ordinance.”
The developer must next submit a final environmental impact statement to the Planning Board, a step near the end of the environmental review process. Acciona’s project would construct 53 turbines with a rated capacity of 79.5 megawatts in the town’s northern agricultural district.
No comments: